Jockey Pump Start and Stop Pressure Settings Explained

Borra Pompes

Set jockey pump pressure controls as a coordinated sequence derived from the approved system pressure and main fire pump start requirement. The jockey pump normally starts before the main fire pump as pressure falls and stops after restoring normal pressure. The main fire pump start point must remain low enough to avoid nuisance starts yet high enough to meet hydraulic and response requirements. There is no universal set of numbers: suction pressure, elevation, churn pressure, pressure regulation, sensing-line location, and device ratings all matter.

Sécurité et périmètre : Les pompes à incendie et leurs entraînements sont des équipements de sécurité des personnes. Les travaux relatifs à l'hydraulique, à l'électricité, au diesel, au carburant, aux batteries, à la pression, aux équipements rotatifs, aux essais et aux pannes doivent respecter la conception approuvée actuelle, les instructions du fabricant, les normes applicables et l'autorité compétente. Ce guide explique le processus de décision en matière d'ingénierie ; il n'autorise pas les modifications sur le terrain, les contournements ou l'exploitation par du personnel non qualifié.

Establish the pressure basis

Use the normal static pressure, source variation, pump curves, elevation, system ratings, and approved hydraulic minimums. Confirm which gauge location defines each setting. Treat this as a system condition rather than an isolated component choice. Identify the source of every input, the unit used, the operating condition it represents, and the person responsible for approval. If information is preliminary, mark the assumption and test how the decision changes at a conservative boundary. This prevents a neat calculation from hiding an uncertain water level, pressure, valve position, driver condition, or simultaneous demand.

For jockey pump pressure settings, verify this section against the selected pump curve, the actual site arrangement, manufacturer instructions, and the current requirements accepted by the authority having jurisdiction. Check the installed condition as well as the drawing because pipe routes, elevations, supports, controls, and access often change during construction. Record the result in a form that can be repeated during commissioning and later inspection. Do not change a safety-critical setting or isolate fire protection without the approved impairment and restoration process.

Arrange the start sequence

As pressure falls, the jockey pump should receive the first maintenance call. Continued pressure loss from a real demand must then initiate the main fire pump. The most useful evidence is measured or approved project data, not a copied rule of thumb. Identify the source of every input, the unit used, the operating condition it represents, and the person responsible for approval. If information is preliminary, mark the assumption and test how the decision changes at a conservative boundary. This prevents a neat calculation from hiding an uncertain water level, pressure, valve position, driver condition, or simultaneous demand.

For jockey pump pressure settings, verify this section against the selected pump curve, the actual site arrangement, manufacturer instructions, and the current requirements accepted by the authority having jurisdiction. Check the installed condition as well as the drawing because pipe routes, elevations, supports, controls, and access often change during construction. Record the result in a form that can be repeated during commissioning and later inspection. Do not change a safety-critical setting or isolate fire protection without the approved impairment and restoration process.

Set jockey stop pressure

Jockey Pump Start and Stop Pressure Settings Explained — design and installation check
Détails de conception et d'installation à vérifier pour ce sujet.

Choose a stop point the jockey pump can reliably reach without excessive deadheading or exceeding system ratings. Check its shutoff head. Review this condition at normal, test, and credible abnormal states before procurement. Identify the source of every input, the unit used, the operating condition it represents, and the person responsible for approval. If information is preliminary, mark the assumption and test how the decision changes at a conservative boundary. This prevents a neat calculation from hiding an uncertain water level, pressure, valve position, driver condition, or simultaneous demand.

For jockey pump pressure settings, verify this section against the selected pump curve, the actual site arrangement, manufacturer instructions, and the current requirements accepted by the authority having jurisdiction. Check the installed condition as well as the drawing because pipe routes, elevations, supports, controls, and access often change during construction. Record the result in a form that can be repeated during commissioning and later inspection. Do not change a safety-critical setting or isolate fire protection without the approved impairment and restoration process.

Protect the main pump start point

Do not set it so low that required residual pressure is lost before starting, or so high that normal pressure variation starts the main pump. The design team should turn this point into a traceable calculation or drawing note. Identify the source of every input, the unit used, the operating condition it represents, and the person responsible for approval. If information is preliminary, mark the assumption and test how the decision changes at a conservative boundary. This prevents a neat calculation from hiding an uncertain water level, pressure, valve position, driver condition, or simultaneous demand.

For jockey pump pressure settings, verify this section against the selected pump curve, the actual site arrangement, manufacturer instructions, and the current requirements accepted by the authority having jurisdiction. Check the installed condition as well as the drawing because pipe routes, elevations, supports, controls, and access often change during construction. Record the result in a form that can be repeated during commissioning and later inspection. Do not change a safety-critical setting or isolate fire protection without the approved impairment and restoration process.

Table de décision pratique

Pressure event Expected response If incorrect, check
Small normal pressure loss Jockey pump starts Sensing line, controller, start setting
Pressure restored Jockey pump stops Stop setting, curve, leakage
Demand exceeds jockey capacity Pressure continues to fall Jockey size and test demand
Main start threshold reached Main fire pump starts Controller and sensing path
Main pump running System follows approved stop logic Controller mode and procedure
Frequent jockey cycles Investigate leakage or control issue Check valves, system volume, settings

Use a reliable sensing line

Verify connection location, valve position, drainage, blockage risk, trapped air, and independence from pressure surges or an unrepresentative local point. Treat this as a system condition rather than an isolated component choice. Identify the source of every input, the unit used, the operating condition it represents, and the person responsible for approval. If information is preliminary, mark the assumption and test how the decision changes at a conservative boundary. This prevents a neat calculation from hiding an uncertain water level, pressure, valve position, driver condition, or simultaneous demand.

For jockey pump pressure settings, verify this section against the selected pump curve, the actual site arrangement, manufacturer instructions, and the current requirements accepted by the authority having jurisdiction. Check the installed condition as well as the drawing because pipe routes, elevations, supports, controls, and access often change during construction. Record the result in a form that can be repeated during commissioning and later inspection. Do not change a safety-critical setting or isolate fire protection without the approved impairment and restoration process.

Understand controller behavior

Jockey Pump Start and Stop Pressure Settings Explained — inspection and commissioning check
Détails d'inspection et de mise en service à documenter avant la livraison.

Review automatic start, manual stop or automatic-stop provisions as applicable, timer functions, alarms, and what happens after power restoration. The most useful evidence is measured or approved project data, not a copied rule of thumb. Identify the source of every input, the unit used, the operating condition it represents, and the person responsible for approval. If information is preliminary, mark the assumption and test how the decision changes at a conservative boundary. This prevents a neat calculation from hiding an uncertain water level, pressure, valve position, driver condition, or simultaneous demand.

For jockey pump pressure settings, verify this section against the selected pump curve, the actual site arrangement, manufacturer instructions, and the current requirements accepted by the authority having jurisdiction. Check the installed condition as well as the drawing because pipe routes, elevations, supports, controls, and access often change during construction. Record the result in a form that can be repeated during commissioning and later inspection. Do not change a safety-critical setting or isolate fire protection without the approved impairment and restoration process.

Diagnose cycling

Trend start and stop pressure, run time, leakage, check-valve condition, pressure tank where used, and gauge calibration before changing settings. Review this condition at normal, test, and credible abnormal states before procurement. Identify the source of every input, the unit used, the operating condition it represents, and the person responsible for approval. If information is preliminary, mark the assumption and test how the decision changes at a conservative boundary. This prevents a neat calculation from hiding an uncertain water level, pressure, valve position, driver condition, or simultaneous demand.

For jockey pump pressure settings, verify this section against the selected pump curve, the actual site arrangement, manufacturer instructions, and the current requirements accepted by the authority having jurisdiction. Check the installed condition as well as the drawing because pipe routes, elevations, supports, controls, and access often change during construction. Record the result in a form that can be repeated during commissioning and later inspection. Do not change a safety-critical setting or isolate fire protection without the approved impairment and restoration process.

Commission with controlled tests

Lower pressure slowly, record the jockey and main pump actions, verify stop behavior and alarms, then restore the system and secure settings. The design team should turn this point into a traceable calculation or drawing note. Identify the source of every input, the unit used, the operating condition it represents, and the person responsible for approval. If information is preliminary, mark the assumption and test how the decision changes at a conservative boundary. This prevents a neat calculation from hiding an uncertain water level, pressure, valve position, driver condition, or simultaneous demand.

For jockey pump pressure settings, verify this section against the selected pump curve, the actual site arrangement, manufacturer instructions, and the current requirements accepted by the authority having jurisdiction. Check the installed condition as well as the drawing because pipe routes, elevations, supports, controls, and access often change during construction. Record the result in a form that can be repeated during commissioning and later inspection. Do not change a safety-critical setting or isolate fire protection without the approved impairment and restoration process.

Comment cela se rapporte à l'équipement BORRAPUMP

BORRAPUMP fournit des équipements de pompage conçus pour des projets liés à l'eau et à la protection contre l'incendie. Examinez le document pertinent Configuration du produit BORRAPUMP à titre de point de départ, puis soumettez le débit, la charge, la source d'eau, l'entraînement, la puissance, les commandes, les conditions du site, les exigences applicables, la quantité et la destination requis. La sélection finale doit utiliser la base hydraulique du projet et la soumission approuvée ; ce guide ne prétend pas qu'une disposition de catalogue convient à toutes les juridictions ou à tous les risques.

Guides BORRAPUMP associés

Références autorisées

Les sources suivantes établissent la limite des normes, le contexte de sécurité incendie et les principes des systèmes de pompes utilisés dans ce guide. Appliquez toujours l'édition et l'adoption locale acceptées pour le projet.

Vidéo éducative

Les pompes créent-elles de la pression ou du débit ?

Formation par Practical Engineering : Les pompes créent-elles de la pression ou du débit ?. La vidéo illustre le concept d'ingénierie sous-jacent et ne remplace pas les exigences de protection contre l'incendie spécifiques au projet.

Foire aux questions

What is the correct jockey pump pressure setting?

Use the project-specific approved sequence; no universal pressure value fits every system.

Should the jockey pump stop automatically?

Follow the listed controller and applicable project requirements. Main and jockey pump stop logic may differ.

Why does the main fire pump start before the jockey pump?

Check sensing lines, controller settings, source pressure changes, and whether the devices measure the same representative system point.

Can I widen the pressure gap to stop cycling?

Only after diagnosing leakage, check valves, system volume, pump curve, and applicable setting limits.

Liste de contrôle de vérification finale

Avant l'approbation, confirmez la base hydraulique, la condition de la source d'eau, la courbe de pompe sélectionnée, les données du moteur et du contrôleur, les pressions nominales des composants, la disposition des vannes, la méthode d'essai, l'accès, le drainage, les alarmes et la procédure de restauration. Résolvez les différences entre les plans et le système installé. Pendant la mise en service, utilisez des instruments étalonnés et enregistrez la pression d'aspiration, la pression de refoulement, le débit, la vitesse, l'état du moteur, les alarmes et les observations anormales à chaque point requis. Conservez les résultats acceptés avec les registres de la salle des pompes afin que les inspections ultérieures comparent des éléments comparables.