Pompa

How to Size a Jockey Pump for a Fire Protection System

Pompa Borra

Size a jockey pump to replace normal system leakage and small pressure losses without meeting sprinkler or hose demand and without repeatedly starting the main fire pump. Determine realistic leakage, system volume and pressure behavior, required pressure, acceptable run time, and the coordinated start-stop sequence. Select a small pump whose curve can reach the intended stop pressure at low flow, then verify that a genuine fire demand produces enough pressure decay to start the main fire pump. Keep the calculation and acceptance record with the final project documents so future tests use the same basis.

Keamanan dan cakupan: Pompa pemadam kebakaran dan penggeraknya adalah peralatan keselamatan jiwa. Pekerjaan hidrolik, kelistrikan, diesel, bahan bakar, baterai, tekanan, peralatan berputar, pengujian, dan gangguan harus mengikuti desain disetujui saat ini, instruksi pabrikan, standar yang berlaku, dan otoritas yang memiliki yurisdiksi. Panduan ini menjelaskan jalur keputusan teknik; panduan ini tidak mengizinkan perubahan lapangan, pengoperasian bypass, atau pengoperasian oleh personel yang не berkualifikasi.

Define the jockey pump's job

It maintains normal system pressure after small losses. It is not a substitute for the main fire pump and should not mask material leakage. Treat this as a system condition rather than an isolated component choice. Identify the source of every input, the unit used, the operating condition it represents, and the person responsible for approval. If information is preliminary, mark the assumption and test how the decision changes at a conservative boundary. This prevents a neat calculation from hiding an uncertain water level, pressure, valve position, driver condition, or simultaneous demand.

For jockey pump sizing, verify this section against the selected pump curve, the actual site arrangement, manufacturer instructions, and the current requirements accepted by the authority having jurisdiction. Check the installed condition as well as the drawing because pipe routes, elevations, supports, controls, and access often change during construction. Record the result in a form that can be repeated during commissioning and later inspection. Do not change a safety-critical setting or isolate fire protection without the approved impairment and restoration process.

Estimate normal leakage

Use maintenance history, measured pressure decay, known valve and device leakage, and system condition. Investigate abnormal leakage instead of permanently oversizing the jockey pump. The most useful evidence is measured or approved project data, not a copied rule of thumb. Identify the source of every input, the unit used, the operating condition it represents, and the person responsible for approval. If information is preliminary, mark the assumption and test how the decision changes at a conservative boundary. This prevents a neat calculation from hiding an uncertain water level, pressure, valve position, driver condition, or simultaneous demand.

For jockey pump sizing, verify this section against the selected pump curve, the actual site arrangement, manufacturer instructions, and the current requirements accepted by the authority having jurisdiction. Check the installed condition as well as the drawing because pipe routes, elevations, supports, controls, and access often change during construction. Record the result in a form that can be repeated during commissioning and later inspection. Do not change a safety-critical setting or isolate fire protection without the approved impairment and restoration process.

Understand system volume

How to Size a Jockey Pump for a Fire Protection System — design and installation check
Detail desain dan instalasi yang perlu diverifikasi untuk topik ini.

Large networks, tanks, and trapped air affect how quickly pressure changes. System compressibility influences cycling but does not create a universal sizing ratio. Review this condition at normal, test, and credible abnormal states before procurement. Identify the source of every input, the unit used, the operating condition it represents, and the person responsible for approval. If information is preliminary, mark the assumption and test how the decision changes at a conservative boundary. This prevents a neat calculation from hiding an uncertain water level, pressure, valve position, driver condition, or simultaneous demand.

For jockey pump sizing, verify this section against the selected pump curve, the actual site arrangement, manufacturer instructions, and the current requirements accepted by the authority having jurisdiction. Check the installed condition as well as the drawing because pipe routes, elevations, supports, controls, and access often change during construction. Record the result in a form that can be repeated during commissioning and later inspection. Do not change a safety-critical setting or isolate fire protection without the approved impairment and restoration process.

Set the required pressure range

The jockey pump must reach the approved stop pressure while its start point remains above the main fire pump start point in the coordinated sequence. The design team should turn this point into a traceable calculation or drawing note. Identify the source of every input, the unit used, the operating condition it represents, and the person responsible for approval. If information is preliminary, mark the assumption and test how the decision changes at a conservative boundary. This prevents a neat calculation from hiding an uncertain water level, pressure, valve position, driver condition, or simultaneous demand.

For jockey pump sizing, verify this section against the selected pump curve, the actual site arrangement, manufacturer instructions, and the current requirements accepted by the authority having jurisdiction. Check the installed condition as well as the drawing because pipe routes, elevations, supports, controls, and access often change during construction. Record the result in a form that can be repeated during commissioning and later inspection. Do not change a safety-critical setting or isolate fire protection without the approved impairment and restoration process.

Tabel keputusan praktis

Sizing input Effect on jockey pump How to verify
Normal leakage Sets required makeup flow Pressure-decay test and history
System volume Affects pressure-change rate Drawings and field behavior
Target pressure Sets required head Approved pressure sequence
Kurva pompa Shows low-flow head capability Manufacturer curve
Check valves Leakage can cause cycling Isolation and leak checks
Saluran pengindera Controls measured pressure Field route and valve position

Check the pump curve

Select against low-flow, high-head operation. Confirm minimum stable operation, shutoff head, motor load, and manufacturer limitations. Treat this as a system condition rather than an isolated component choice. Identify the source of every input, the unit used, the operating condition it represents, and the person responsible for approval. If information is preliminary, mark the assumption and test how the decision changes at a conservative boundary. This prevents a neat calculation from hiding an uncertain water level, pressure, valve position, driver condition, or simultaneous demand.

For jockey pump sizing, verify this section against the selected pump curve, the actual site arrangement, manufacturer instructions, and the current requirements accepted by the authority having jurisdiction. Check the installed condition as well as the drawing because pipe routes, elevations, supports, controls, and access often change during construction. Record the result in a form that can be repeated during commissioning and later inspection. Do not change a safety-critical setting or isolate fire protection without the approved impairment and restoration process.

Limit short cycling

How to Size a Jockey Pump for a Fire Protection System — inspection and commissioning check
Detail inspeksi dan komisioning untuk didokumentasikan sebelum serah terima.

Review check-valve leakage, pressure-tank function where used, sensing line location, system volume, and the gap between start and stop settings. The most useful evidence is measured or approved project data, not a copied rule of thumb. Identify the source of every input, the unit used, the operating condition it represents, and the person responsible for approval. If information is preliminary, mark the assumption and test how the decision changes at a conservative boundary. This prevents a neat calculation from hiding an uncertain water level, pressure, valve position, driver condition, or simultaneous demand.

For jockey pump sizing, verify this section against the selected pump curve, the actual site arrangement, manufacturer instructions, and the current requirements accepted by the authority having jurisdiction. Check the installed condition as well as the drawing because pipe routes, elevations, supports, controls, and access often change during construction. Record the result in a form that can be repeated during commissioning and later inspection. Do not change a safety-critical setting or isolate fire protection without the approved impairment and restoration process.

Coordinate controls and alarms

Keep the sensing line independent and correctly arranged, protect it from blockage or trapped air, and document controller modes and alarm response. Review this condition at normal, test, and credible abnormal states before procurement. Identify the source of every input, the unit used, the operating condition it represents, and the person responsible for approval. If information is preliminary, mark the assumption and test how the decision changes at a conservative boundary. This prevents a neat calculation from hiding an uncertain water level, pressure, valve position, driver condition, or simultaneous demand.

For jockey pump sizing, verify this section against the selected pump curve, the actual site arrangement, manufacturer instructions, and the current requirements accepted by the authority having jurisdiction. Check the installed condition as well as the drawing because pipe routes, elevations, supports, controls, and access often change during construction. Record the result in a form that can be repeated during commissioning and later inspection. Do not change a safety-critical setting or isolate fire protection without the approved impairment and restoration process.

Commission the sequence

Create a controlled small pressure loss, verify jockey start and stop, then create the approved larger demand and verify main pump start without delay. The design team should turn this point into a traceable calculation or drawing note. Identify the source of every input, the unit used, the operating condition it represents, and the person responsible for approval. If information is preliminary, mark the assumption and test how the decision changes at a conservative boundary. This prevents a neat calculation from hiding an uncertain water level, pressure, valve position, driver condition, or simultaneous demand.

For jockey pump sizing, verify this section against the selected pump curve, the actual site arrangement, manufacturer instructions, and the current requirements accepted by the authority having jurisdiction. Check the installed condition as well as the drawing because pipe routes, elevations, supports, controls, and access often change during construction. Record the result in a form that can be repeated during commissioning and later inspection. Do not change a safety-critical setting or isolate fire protection without the approved impairment and restoration process.

Bagaimana ini terkait dengan peralatan BORRAPUMP

BORRAPUMP memasok peralatan pompa rekayasa untuk proyek-proyek air dan proteksi kebakaran. Tinjau yang relevan Konfigurasi produk BORRAPUMP sebagai titik awal, lalu serahkan aliran, tinggi tekan, sumber air, penggerak, daya, kontrol, kondisi lokasi, persyaratan yang berlaku, jumlah, dan tujuan yang diperlukan. Pemilihan akhir harus menggunakan dasar hidrolik proyek dan submittal yang disetujui; panduan ini tidak mengklaim bahwa satu susunan katalog cocok untuk setiap yurisdiksi atau risiko.

Panduan BORRAPUMP terkait

Referensi otoritatif

Sumber-sumber berikut menetapkan batas standar, konteks keselamatan kebakaran, dan prinsip sistem pompa yang digunakan dalam panduan ini. Selalu terapkan edisi dan adopsi lokal yang disetujui untuk proyek tersebut.

Video edukasi

Apakah Pompa Menghasilkan Tekanan atau Aliran?

Latar belakang pendidikan oleh Practical Engineering: Apakah Pompa Menghasilkan Tekanan atau Aliran?. Video tersebut mendukung konsep teknik yang mendasar dan tidak menggantikan persyaratan perlindungan kebakaran khusus proyek.

Pertanyaan yang sering diajukan

Can I size a jockey pump as a percentage of the fire pump?

Do not rely on a percentage alone. Use actual leakage, system pressure behavior, the jockey curve, and approved criteria.

Why does the jockey pump short-cycle?

Possible causes include leakage, check-valve backflow, small system volume, trapped air, pressure-tank problems, or narrow settings.

Should the jockey pump handle sprinkler flow?

No. A fire demand must start the main fire pump according to the approved sequence.

Can an oversized jockey pump delay the main pump?

It can mask a growing demand or create poor control behavior, so size and test the complete sequence.

Daftar periksa verifikasi akhir

Sebelum persetujuan, konfirmasikan basis hidrolik, kondisi sumber air, kurva pompa yang dipilih, data penggerak dan pengontrol, peringkat tekanan komponen, susunan katup, metode pengujian, akses, drainase, alarm, dan prosedur pemulihan. Selesaikan perbedaan antara gambar kerja dan sistem yang terpasang. Selama pengujian (commissioning), gunakan instrumen yang dikalibrasi dan catat tekanan isap, tekanan buang, aliran, kecepatan, kondisi penggerak, alarm, dan pengamatan tidak normal pada setiap titik yang diperlukan. Simpan hasil yang diterima bersama catatan ruang pompa sehingga pemeriksaan selanjutnya dapat membandingkan hal yang setara.